Phoenix Ironworks

Littleborough



This development has transformed a former brownfield site and brought 20 much needed new homes to Littleborough, all for affordable rent.

We've transformed a former brownfield site and bring 20 much needed new homes to Littleborough, all for affordable rent.

Housing mix:

20 new properties which will be a mixture one bedroom apartments, and two and three bedroom homes:

4 one bedroom apartments

8 two bedroom homes

8 three bedroom homes

 

Tenure:

All the homes will be for affordable rent.

 

Key dates:

Start on site: September 2020

Practical completion: December 2021

 

Total scheme cost:

£3.3 million

Homes England grant total: £760,0000

 

Partners

Main contractor: Casey

Employer’s Agent: Whiteley Eaves Ltd

The 20 new properties will be a mixture one bedroom apartments, and two and three bedroom homes.